News & Milestones

The Axiom timeline.

Major milestones in Axiom's progress from concept to commercial operations. Updated as material developments occur.

Recent Milestones

Key validations.

March 2026
Technical Validation
Validation

Shell Upgrader Technology validates Axiom biocrude specification

Shell's Upgrader Technology team independently completed validation of the biocrude feedstock specification and the projected product yields from the Axiom upgrading process. Validated yields confirmed at 65 vol% SAF, 30 vol% light naphtha, 5 vol% heavy diesel.

The validation removes the single largest technology risk in early-stage SAF projects and is a precondition for both the upgrading technology licence finalisation and senior debt mandate.

February 2026
Brand & Corporate
Corporate

Axiom Global Fuels Ltd incorporated; brand identity finalised

The UK holding entity, Axiom Global Fuels Ltd, was formally established as the parent company for the Indian operating SPVs. Brand identity, tagline ("Beyond Doubt. Beyond Fossil.") and visual language finalised in parallel.

January 2026
Feedstock
Feedstock

Upstream feedstock network reaches five Indian states

Contracted upstream biocrude supply expanded across Madhya Pradesh, Gujarat, Andhra Pradesh, Uttar Pradesh and Punjab — totalling 1.8 million tonnes of contracted feedstock access, rising to 3.6 million tonnes at full network operations.

Forward Roadmap

The next 24 months.

Critical-path milestones to first SAF delivery, in execution order.

Q2–Q3FY2026

Seed Round Close · FEED Initiation

USD 2.5MM convertible note closes. Catalytic upgrading licensor FEED engagement and Indian EPC partner appointed. Independent engineer commissioned.

Q3FY2026

Senior Hires · MNRE Filing

CTO, CFO and India Country Manager appointed. MNRE bioenergy grant application submitted. Gujarat PCB environmental scoping initiated.

Q4FY2026

Plant 1 Financial Close

USD 27.5MM equity close (Series A). USD 51MM senior debt mandate (IREDA + IFC + BII PCG). Convertible note converts. EPC contract executed.

Q1FY2027

Plant 1 Construction Start

Site mobilisation at Hazira. 24-month construction programme commences. Core equipment manufacturing initiated.

Q1FY2028

First SAF Delivery

Plant 1 commercial operations begin. First Axiom SAF delivered to offtake counterparties. CORSIA-eligible credits issued.